Urban Ring Project (MBTA)
The Urban Ring was a proposed project of the Massachusetts Bay Transportation Authority and the Massachusetts Department of Transportation, to develop new public transportation routes that would provide improved circumferential connections among many existing transit lines that project radially from downtown Boston. The Urban Ring Corridor is located roughly one to two miles from downtown Boston, passing through the Massachusetts cities of Boston, Chelsea, Everett, Medford, Somerville, Cambridge, and Brookline. The project was expected to convert 41,500 car trips to transit trips daily.
The Major Investment Study split the project into three phases, the first of which was partially implemented. The planning of Phase 2 was suspended in January 2010 because MBTA and the Commonwealth of Massachusetts have insufficient funding to build a substantial portion of that phase. , some interim bus service improvements have been implemented or are underway, in the absence of major funding.
Background
Transportation advocates in Boston have complained that rail transit riders cannot travel from one outlying area to another without first traveling to the downtown hub stations, changing lines, and traveling outbound again. Some of the radial transit lines, notably the Green Line, are so overcrowded that service is very slow and limited in capacity because of rush-hour "crush loads". There are several crosstown bus lines, such as the #1, #66, CT1, CT2, and CT3 routes, but they are slow, unreliable, and subject to bus bunching because they must operate in mixed street traffic.A circumferential rapid transit line was proposed by the City of Boston as early as 1923, and circumferential transit has been studied as early as 1972, in the Boston Transportation Planning Review. Detailed proposals were not studied until the late 1990s.
Project proposal
The proposed project has three phases. The first phase has been partially implemented. Phase 1, as it is commonly called, involves expanding "crosstown" bus lines serving the entire corridor and "express commuter" lines connecting to suburban locations. Phase 2 would create six overlapping bus rapid transit lines forming a complete ring around downtown Boston. Phase 3 includes the implementation of rail service on the most heavily traveled portion of the ring, from Assembly Square in southeastern Somerville to Dudley Square in the Roxbury neighborhood of Boston, via East Cambridge.Phase 1
Phase 1 as recommended in the Major Investment Study, would expand the "crosstown" bus system by extending and increasing frequency on the three existing lines, and by adding eight new lines. It also adds "express commuter" lines for connections to locations outside the corridor. Estimated ridership according to the Phase 2 DEIR would have been 40,000 for 2003, at a capital cost of $100 million, for low-floor, low-emissions buses.The MBTA determined that Phase 1 of the Urban Ring project did not meet the threshold requirements for an extensive environmental review, and so can be implemented as a part of its normal service planning process. However, of the eleven CT routes and three EC routes proposed, only CT1, CT2, and CT3 were running as of 2014.
Phase 2
Draft EIR
The MBTA filed the Draft Environmental Impact Report for Phase 2 with the Massachusetts Environmental Policy Act Office on November 30, 2004. In its FY2005-10 and draft FY2006-11 Capital Improvement Plans, the MBTA has not budgeted any money for the Urban Ring project, beyond supporting the EIR process.Phase 2 would convert and expand five of the "crosstown" lines into bus rapid transit lines that overlap and form a complete ring around the urban core.
- BRT 1: Airport Station to Kendall Square via Wellington, Assembly Square, Sullivan Square, and Lechmere
- BRT 2: Logan Airport Terminals to Wellington with local service to Chelsea and Everett
- BRT 3: Wellington to Kendall via Gilman Square, Union Square Somerville, and Lechmere
- BRT 5: Lechmere to Ruggles via Kendall, Grand Junction/MIT, BU Bridge, Kenmore/Yawkey/Fenway, and Huntington Avenue
- BRT 6: Commonwealth Ave at Boston University Central to UMass Boston via Ruggles, Melnea Cass Blvd, Uphams Corner
- BRT 7: Longwood Medical Area to Mystic Mall via South Boston, World Trade Center, Ted Williams Tunnel, and Downtown Chelsea
- Downtown Chelsea
- Yawkey
- Ruggles
- Sullivan Square
- Gilman Square
- Union Square
Some parts of the BRT system would run in mixed traffic, including through the Ted Williams Tunnel and to the terminals at Logan International Airport. Dedicated lanes would be provided for certain portions, including:
- The Grand Junction Railroad right-of-way, which runs through the campus of the Massachusetts Institute of Technology and crosses the Charles River under the Boston University Bridge
- Railroad right-of-way in Somerville, connecting with Lechmere
- Portions from East Boston to Chelsea
- Melnea Cass Boulevard, connecting the Silver, Orange, and Green Lines
- The Haul Road in South Boston
2008 revised draft EIR
, the revised route of the ring had the following stops:Station | Existing Connections | City / Neighborhood | Notes |
Logan International Airport | East Boston | West Garage | |
East Boston | |||
Griffin Way | Chelsea | ||
Chelsea station | Chelsea | ||
Mystic Mall | |||
Everett / Massachusetts Route 16 / Gateway Center | Everett | ||
and bus hub | Medford | ||
Somerville | |||
and bus hub | Charlestown | Proposed Commuter Rail Stop | |
Inner Belt Road | Somerville | ||
Cambridge | Station relocation part of Green Line Extension Project; under construction | ||
First Street / Cambridgeside Galleria | Cambridge | ||
Binney Street | Cambridge | ||
Fulkerson Street | Cambridge | Served only by one of the BRT routes, the others would go direct to Kendall | |
Cambridge | |||
Massachusetts Avenue / Massachusetts Institute of Technology | Cambridge | Via Albany Street | |
Cambridgeport at George Washington Park | Cambridgeport | Crossing into Grand Junction Railroad right-of-way | |
Commonwealth Avenue at Boston University Bridge | Boston | Via widened Grand Junction Railroad bridge | |
Boston | |||
Boston | Minor spur served by only 1 BRT route | ||
Boston | Underground station proposed | ||
and bus hub | Boston | ||
Washington Street at Melnea Cass Boulevard | Roxbury | ||
and bus hub | Roxbury | ||
Crosstown Center | Dorchester | ||
BU Medical Center | Boston | ||
South Boston | Unused streetcar tunnel segment above Red Line tracks | ||
A Street | South Boston | ||
South Boston |
This routing skipped Gilman and Union Squares in Somerville, but these locations would be connected to the new Lechmere Station via the Green Line Extension. The Grand Junction Railroad crossing of the Charles River would be widened to include bus lanes and a multi-use path.
There would be two major spurs. Three different routings were being considered for the first spur, on the west side of the ring, which would leave from Commonwealth Avenue and go to:
- Allston West Station
- North Harvard Street
- Western Avenue
- , Red Line
- Newmarket Square
- Edward Everett Square, Dorchester
- JFK/UMass, Red Line
An interim surface routing was proposed, with multiple stops in the Longwood Medical Area, while the tunnel would be under construction.
The capital cost for this version of the plan was estimated at $2.2 billion, with a projected daily ridership of 170,000. Approximately 53% of the route was either in a bus-only lane, dedicated busway, or tunnel. This was increased from the previous plan for Phase 2, to improve travel times. As a result of the implementation of Phase 2, ridership growth on the Red, Orange, Blue, and Green lines would be slowed, but Commuter Rail ridership boosted. The Urban Ring would have a higher collective ridership than the Orange Line, Blue Line, or the entire Commuter Rail system.
Phase 3
Phase 3 would add a rail line on the most heavily traveled portion of the corridor, from Assembly Square in Somerville to Lechmere, Kendall Station, crossing Massachusetts Avenue near MIT, and connecting at Longwood Medical a, Ruggles, and Dudley Square. The exact alignment would be determined through further environmental review, and included possible stops in Union Square Somerville, Cambridgeport and/or Kenmore Square, and a possible new tunnel under the Charles River.There were three alternatives being considered for Phase 3, which differed from the alternatives described in the Major Investment Study and Draft Environmental Impact Review. Employment growth projections have also changed since those documents were written.
The three proposed options for what type of rail service to build were:
- A light rail branch of the Green Line, mostly on the surface
- A light rail branch of the Green Line, entirely subway
- A heavy rail branch of the Orange Line, entirely subway