Texas State Highway Loop 1


Loop 1 is a freeway which provides access to the west side of Austin in the U.S. state of Texas. It is named Mopac Expressway after the Missouri Pacific Railroad. Local residents will invariably use the name "MoPac" rather than calling the road by its number which can cause much confusion as few signs along the road use this name.
The original section of the highway was built in the 1970s along the right-of-way of the Missouri Pacific Railroad, with the railroad tracks running in the highway median between West 8th Street and Northland Drive. To the north, the tracks run along the east side of newer sections of the highway from Northland Drive to Braker Lane.

History

Route designation

The first mention of Loop 1 came to public record in 1929. In 1944, the City of Austin Planning Commission proposed the highway be built in parts of under-utilized right of way owned by the MoPac railroad. Thus, the highway was eventually given the nickname "MoPac" for its proximity to the railroad.
The number was originally used for Spur 1 designated on September 26, 1939 from US Highway 90 to the Uvalde fish hatchery as a renumbering of SH 3 Spur. This route was cancelled on December 16, 1943. On March 26, 1958, a new route was designated, also called Spur 1, from US 80A to I-10. This route became part of Loop 16 on July 31, 1964, which itself got cancelled on June 26, 1974 when it was transferred to rerouted US 62 and US 85.
Loop 1 was first designated on October 27, 1967 from US 290 northward to Farm to Market Road 1325. On October 24, 1985, the designation was extended southward from US 290 to SH 45.

Expressway construction (1969 to 2006)

This table contains the dates of the construction of segments of the road.
FromToLength
Length
Year
project began
Year of
project completion
Notes
RM 2244
RM 2222
February 1969November 1975Loop 1 project started with
construction of the 45th Street
Interchange in February 1969.
-
RM 2222US 183September 1977June 1981Northern terminus of Loop 1 completed,
until July 1989 - with construction of the freeway extension to FM 734.
-
RM 2244Loop 360January 1979March 1982Southern terminus of Loop 1 completed,
until October 1989 - with construction of the freeway extension to US 290.
-
Loop 360US 290October 1983October 1989Southern terminus of Loop 1 completed,
until November 1990 - with construction of the roadway
extension to Slaughter Lane.
-
US 183FM 1325
and FM 734
January 1986July 1989Northern terminus of Loop 1 completed,
until October 2006 - with construction of the SH 45 North/
Loop 1 Connector toll road.
Stack interchange at US 183 is constructed -
involved major freeway improvements between Steck Avenue and US 183,
from March 1987 to June 1992.
-
US 290Slaughter LaneJanuary 1988November 1990Southern terminus of Loop 1 completed,
until July 1991 - with construction of the roadway
extension to La Crosse Avenue.
-
Slaughter LaneLa Crosse AvenueJuly 1989July 1991Southern terminus of Loop 1 completed,
until May 1994 - with construction of the roadway
extension to State Highway 45.
-
La Crosse AvenueSH 45November 1989May 1994Southern terminus of Loop 1 completed.-
FM 734SH 45 North/
Loop 1 Interchange
February 2003October 2006Construction on the SH 45 North Interchange
began in September 2003.
Northern terminus of Loop 1 completed.
-

Route description

Loop 1's southern terminus is at the beginning of the State Highway 45 stub south of Austin. It passes through the Circle C Ranch housing development and the Edwards Aquifer and intersects SH 71/US 290 and Loop 360. It crosses the Colorado River near downtown Austin; the view of the Texas State Capitol from the bridge became one of the Capitol View Corridors protected under state and local law from obstruction by tall buildings in 1983. North of the river, the highway runs parallel to the Balcones Fault and the Missouri-Pacific Railroad before intersects US 183 northwest of downtown. Loop 1 travels concurrently with Farm to Market Road 1325 for several miles before the non-tolled freeway ends at Parmer Lane, spanning a distance of 22.061 miles.
North of Parmer Lane, Loop 1 continues as a limited-access toll road to the SH 45 North/Loop 1 interchange, spanning. Frontage roads flank either side of the toll road to Merrilltown Drive.
The Texas Department of Transportation completed construction of the tollway as part of the 2002 Central Texas Turnpike Project. SH 45 North, also part of the project, provides freeway access to Interstate 35 from Loop 1. The 2002 CTTP was scheduled to be completed in September 2007. However, certain sections of the project, including Loop 1 opened early and more than $100 million under budget.
If and when SH 45 is completed to the south of Austin, Loop 1 will effectively serve as a true loop to the west of the city, being directly connected to SH 45, and indirectly to I-35, at both ends.

MoPac Improvement Project

Since 1994, TxDOT has proposed the addition of managed lanes to portions of Loop 1. The MoPac Improvement Project was relaunched in July 2010. In December 2010, four alternative proposals were presented to the public, each of which would add one or more lanes; the "no-build" alternative was also presented.
The additions would not increase the right-of-way of the highway, but would be created by reducing the width of existing lanes and reducing and/or eliminating shoulders.
An environmental study was completed in August 2012 with a Finding Of No Significant Impact and a recommendation of one new travel lane in each direction, operated as express lanes.
Construction began in 2013, and was originally scheduled for completion in September 2015, but by August 2016, the Central Texas Regional Mobility Authority announced further delays.
The first of four tolled sections, specifically the northbound toll lane from RM 2222 to Parmer Lane, opened on October 17, 2016. The remainder of the northbound express lane, from Cesar Chavez Street to Parmer Lane, opened on October 7, 2017, and the entire southbound express lane opened on October 28, 2017.

MoPac Intersections Project

In 2013, the Central Texas Regional Mobility Authority and TxDOT initiated an environmental study to analyze the best options to improve the MoPac intersections at Slaughter Lane and La Crosse Avenue. In December 2015, the study was completed with a Finding Of No Significant Impact for the project, which allowed it to move forward. The selected design included replacing the at-grade intersection at Slaughter Lane with a diverging diamond interchange and the at-grade intersection at La Crosse Avenue with a diamond interchange. The project broke ground in January 2018 with Webber, LLC as the general contractor.
On August 10, 2018, the existing Slaughter Lane intersection was rerouted to the south. The original intersection was replaced with a bridge over the new Mopac mainlanes. The DDI opened on November 11, 2018, with final completion expected by Spring 2019. The La Crosse Avenue intersection began construction in Fall 2018. On March 29, 2019, the La Crosse Avenue intersection was closed for reconstruction as a bridge. The La Crosse intersection is expected to be completed in 2020. The project as a whole is expected to be completed in 2021.