Sunkoshi Small Hydropower Plant


Sunkoshi Small Hydropower Plant is located in Dhuskun of Sindhupalchok District in central Nepal. It downstream where the Sunkoshi and Bhotekoshi Rivers meet. Construction on the plant began in 2003 and it was complete in 2005.
The plant is a Run- Of- River project with installed capacity of 2.5 MW, design flow of 2.7 m3/s and gross head of 124.5m.
This is only project in Nepal to utilize pressurized Glass Fibre reinforced Plastic pipe for flow conduction.
The plant has two units with Turgo turbine. The power is evacuated via 33kVA transmission line to switch-yard of Sunkoshi Power Plant
The plant was completely submerged by 2014 Sunkoshi blockage.