On 2 June 2009, a major part of the roof construction collapsed under normal weather conditions, including the section above the royal box. It was only about a year after the stadium was officially opened. Witness accounts indicated that a long loud sound similar to a jet engine noise was heard as the roof fell to earth in pieces. A number of staff were in the stadium during the collapse, with preparations for varsity staff games being made. In addition to the games getting cancelled, many pieces of equipment were either damaged or destroyed and vehicles parked nearby being damaged. Fortunately, no casualties were reported. The major cause for the collapse of the roof was identified to be the design fault and inappropriate materials. There were also reports of sporadic loud bangs and structure damage prior to the collapse. One of the structural repair jobs on the roof was scheduled on the day of the collapse itself, along with some electrical repair works being carried out on other part of the stadium. As of June 2010, the cleaning work and relocation of the collapsed roof were not finished. On 19 December 2011 Terengganu Menteri BesarAhmad Said confirmed that the stadium would be repaired by early 2012 with alterations to its roof design, mulling it to be similar with that of the Bukit Jalil National Stadium.
Second Collapse of the roof
On 20 February 2013 the stadium collapsed again while undergoing re-construction work which commenced late 2012. 137 meters collapsed when working construction workers heard loud noises, followed by the collapse of steel pillars. The collapse cause injuries to 5 workers with 3 of them suffering serious injuries. In October 2014, the stadium undergo a RM26 million repair funded by the Terengganu state government and supervised by the Public Works Department involving 14 contractors. In early January 2018, the stadium roof will undergo re-construction again.
Upgrading the Football Pitch
In April 2019, as part of the Malaysian Football League initiative to improve the quality of Malaysian Football, the stadium football pitch were upgraded through MFL pilot project to restore field quality. The stadium pitch is now being carpeted with Bermuda grass and the re-turfing cost RM1 million, sponsored by MFL. On 1 February 2020, the damaged running track cause by the collapse of roof will be replaced with artificial grass and will look exactly like the Tan Sri Dato' Haji Hassan Yunos Stadium. As a result of this, the stadium will be dedicated for football use only.
Events
2008 Sukma Games: Terengganu
Politics
The stadium's fate was overseen by Malaysian Opposition as a part of the administration by the former Barisan Nasional government led by then Menteri Besar Idris Jusoh. Idris was removed from Wisma Darul Iman following a fallout with the Terengganu Palace shortly after the 2008 General Elections, an event that formed the background of the 2008 Terengganu Constitutional Crisis. One of his replacement, Ahmad Said's early duties was to attend the officiating of the stadium, a project closely overseen by him.