Shenyang–Dandong intercity railway is long with new rail lines making up of its length. The project was a joint venture project between the former Chinese Ministry of Railways and the Liaoning Provincial Government, jointly investing a total of 26.88 billion yuan, consisting of 24.88 billion yuan for rail construction and rolling stock acquisition costing 2 billion yuan. Works started on March 17, 2010, was completed before September 2015. After the opening of the railway the journey from Shenyang to Dandong has been shorten from 3.5 hours travel time to just over one hour. The railway runs from Shenyang, via Benxi to Dandong. It allows for connections with the Beijing–Shenyang high-speed railway and the Harbin–Dalian high-speed railway, plus other conventional railways and other intercity rail services. The route crosses several environmentally sensitive areas, such as the Shenyang Sujiatun District, Ma'er Mountain Biodiversity for afforestation, the Benxi Ring National Forest Park, Benxi National Geopark, Damingshan fissure ancient volcanic nature reserve, Dandong Tongyuanpu pine biomes natural five key areas of protected areas. Environmental protection is an essential and demanding part of the overall project. The railway features a total of 86 large and medium bridges, for a combined distance of about, accounting for 32.51% of the railway's length. The Shen 1st Avenue Bridge is the longest on the route, with a length of 2896 m and a maximum span of 128 meters. Sixty-three tunnels with a total length of, account for 41.9% of the total length of the line. The longest tunnel being Nanfen, 7349 meters long. Bridges and tunnels together account for 80.5% of the line length.
History
Before construction phase
In early 2008 – The Liaoning provincial government put forward to strengthen the Liaoning coastal economic belt by constructing a railway network, officially launching the project and the project's preparatory work
July 2008 – The project was included by the Ministry of Railways as part of the Liaoning urban intercity railway network planning projects
October 10, 2008 – Ministry of Railways and the provincial government signed the "On accelerating the construction of railways in Liaoning Minutes", with the railway included into the long-term railway network plan, with an initial standard for an electric railway, two-way traffic, travelling at more than.
November 25, 2008 – The Liaoning Provincial Development and Reform Commission held a coordination meeting, scheduling to start construction in 2009
January 11, 2009 – The 3rd Institute of the China Railway Group complete the preparation of pre-feasibility report and its review by the Ministry of Railways