Sandpiper pipeline


The Sandpiper pipeline is a underground oil pipeline project in the United States. It would carry light crude oil from the Bakken oil fields in Northwest North Dakota, through Minnesota, to end in Superior, Wisconsin. Enbridge Energy Partners, and Williston Basin Pipe Line LLC, an indirect subsidiary of Marathon Petroleum Corporation have been planning the project since 2013. In 2015 Enbridge estimated the pipeline will cost about $2.6 billion.

History

The Sanpiper pipeline project was made public by the media in 2013, and informational hearings for landowners took place in three North Dakota towns during March 2014. The North Dakota Public Service Commission approved the pipeline in June 2014. The Minnesota Public Utilities Commission unanimously approved the Sandpiper pipeline, but its decision was overturned in September 2015.
In September 2016, Enbridge Energy Partners announced that due to "extensive and unprecedented delays have plagued the Sandpiper pipeline," they were withdrawing their state application and asking for an end to regulatory proceedings, including work on an environmental-impact statement. An Enbridge spokesperson said that the pipeline may be reconsidered once the oil market rebounds but it was then "outside the company’s current five-year planning horizon".

Purpose

In 2015, Enbridge stated that "The Sandpiper Pipeline serves the oil conducting needs of North Dakota residents, which constitutes a public benefit". Per Enbridge, the Sandpiper pipeline represents a "public use", a "statutorily defined public utility.", and its route was chosen with the "greatest public benefit and the least private injury." and "As long as the public benefit can be demonstrated, it is immaterial that private interests are also served."
Per Enbridge, the pipeline is necessary "to meet demand for Bakken oil".
The corporation projects economic benefits of $69 million in property tax revenue for the 3 states, and 3000 construction jobs for workers in Minnesota and North Dakota.

Description

The pipeline would enter Minnesota just south of Grand Forks, North Dakota, east to Clearbrook Enbridge's terminal. and then south toward Park Rapids along an existing crude oil corridor. Afterwards, the pipeline would run in a transmission line corridor to Superior, Wisconsin.
The route passes through 28 rivers, including the Mississippi River headwaters, and lakes and wetlands that can’t be reached by nearby roads if a spill should occur.

North Dakota portion

Informational hearings for landowners took place in three North Dakota towns during March 2014. The North Dakota Public Service Commission approved the pipeline on 25 June 2014.
Enbridge sued a couple in Grand Forks in 2014, because they refused to give Enbridge an easement and right-of-way. the couple quoted NDPL's abuse of eminent domain, continued reliance on fossil fuels their effect on the environment and possibility for spills as arguments. In August 2015 the couple agreed on an easement, and forfeited compensation, in order to file an appeal to the North Dakota Supreme Court.

Minnesota portion

In November 2013, Enbridge applied at the Minnesota Public Utilities Commission. The MPUC unanimously approved the project, allowing to do an environmental review later. In September 2015, the