Construction of the plant began in 1993, and was originally expected to be completed in 1997, but the completion date has been postponed 23 times by 2017. Construction and testing of the facility were complete in 2013 according to JNFL, and the site was intended to begin operating in October 2013; however this was delayed by new safety regulations. In December 2013 JNFL announced the plant would be ready for operation in October 2014. In 2015, the start of the reprocessing plant was postponed again, this time to as late as September 2018. In December 2017, the completion date was put back a further three years, to 2021, to allow for further safety measures at the reprocessing plant and the MOX fuel fabrication plant to meet post-Fukushima safety standards. The delays have caused many parts of the plant to deteriorate, and the closure of the unsuccessful fast breeder reactor at Monju in 2016 reduces the need for the policy of nuclear fuel reprocessing. In August 2018 more corroded pipes were found. In 2018 the Japanese Atomic Energy Commission updated plutonium guidelines to try to reduce plutonium stockpiles, stipulating that Rokkasho should only produce the amount of plutonium required for mixed oxide fuel for Japan's nuclear plants.
Description
The Rokkasho plant is the successor to a smaller reprocessing plant located in Tōkai, Ibaraki in central Japan, which ceased operation in 2007. The Rokkasho facilities complex includes:
In 2010, the Rokkasho complex consisted of 38 buildings on an area of 3,800,000 m². Vitrification tests completed in November 2007. This consists of pouring high level dry waste residue along with molten glass into steel canisters. As of 2018, over a third of Japan's 10 metric tons of domestically held plutonium is stored at Rokkasho.
Economic aspects
Since 1993 there has been US$20 billion invested in the project, nearly triple the original cost estimate. A 2011 estimate put the cost at US$27.5 billion.
Protests
In May 2006, an international awareness campaign about the dangers of the Rokkasho reprocessing plant, Stop Rokkasho, was launched by musician Ryuichi Sakamoto. Greenpeace has opposed the Rokkasho Reprocessing Plant under a campaign called "Wings of Peace – No more Hiroshima Nagasaki", since 2002 and has launched a cyberaction to stop the project. Consumers Union of Japan together with 596 organisations and groups participated in a parade on 27 January 2008 in central Tokyo against the Rokkasho Reprocessing Plant. Over 810,000 signatures were collected and handed in to the government on 28 January 2008. Representatives of the protesters, which include fishery associations, consumer cooperatives and surfer groups, handed the petition to the Cabinet Office and the Ministry of Economy, Trade and Industry. Seven consumer organisations have joined in this effort: Consumers Union of Japan, Seikatsu Club Consumer's Co-operative Union, Daichi-o-Mamoru Kai, Green Consumer's Co-operative Union, Consumer's Co-operative Union "Kirari", Consumer's Co-operative Miyagi and Pal-system Co-operative Union. 'Experts including Frank von Hippel, a Princeton University theoretical physicist, have urged Japan to stop spent fuel reprocessing.', reported The Japan Times. The fundamental objection to reprocessing—the separation of plutonium from spent power reactor fuel—is that the plutonium is a nuclear explosive. Despite nuclear industry claims to the contrary, it usable for powerful nuclear weapons. A plant like Rokkasho can separate several tons of plutonium per year. a nuclear weapon requires only several kilograms.
In June 2008, several scientists stated that the Rokkasho plant is sited directly above an active geological fault line that could produce a magnitude 8 earthquake. But Japan Nuclear Fuel Limited stated that there was no reason to fear an earthquake of more than magnitude 6.5 at the site, and that the plant could withstand a 6.9 quake. After the Tōhoku earthquake in March 2011, the plant ran on emergency power provided by backup diesel generators. The emergency generators were not intended for long-term use. Reportedly there are about 3,000 tons of highly radioactive used nuclear fuel stored in Rokkasho at the current time. Japanese radio reported on 13 March that 600 liters of water leaked at the Rokkasho spent fuel pool. According to The New York Times, grid power was restored on 14 March 2011. The 7 April aftershock caused the loss of grid power again until the next day.