The spar and the topsides of the Perdido were constructed separately and then assembled in its final position in the Gulf of Mexico. The Perdido's hull or spar was constructed by Technip in Pori, Finland. A barge shipped the 22,000 tonne spar 13,200 kilometres from the Baltic Sea to the Gulf of Mexico. After floating the spar, it was towed to its final home above the Alaminos canyon 320 kilometres from the shore. The spar was rotated by the Balder from a horizontal to a vertical floating position by pumping water through hoses attached to the spar. It was then anchored by the Balder to piles in the seafloor. The platform has three decks or topsides which support the oil and gas processing units, a drilling rig and living quarters for the workers. The topsides were designed by Alliance Engineering and constructed by Kiewit Offshore in Corpus Christi, Texas. The temperature difference between Finland and Texas posed a challenge in assembling the pieces as the components built in cold of northern Europe expand in the heat of the Gulf of Mexico. Computer-guided lasers marked out the measurements to ensure precision. After the decks were constructed, in March 2009 the Thialf lifted the 9,500 tonne topsides onto four posts on the spar and slotted it into position.
Technology
Operated by Shell, with JV partners Chevron and BP, the spar acts as a hub for and enables development of three fields Great White, Tobago, and Silvertip. The oil and gas fields beneath the platform lie in a geological formation holding resources estimated at 3-15 billion barrels of oil equivalent according to a report by the BSEE, formerly known as the MMS. At peak production, Perdido processes 100,000 barrels of oil equivalenta day, and 200 million cubic feet of gas.
Operation
The twenty-two oil wells that the Perdido extracts oil from are connected to a 44 kilometre network of pipelines on the ocean floor that link it to five flexible pipes called risers. A workforce of 172 people keep it up and running. They work in 12-hour shifts for 2 weeks followed by 2 weeks off, back on land.
Safety
The platform has extensive safety equipment to protect workers in this remote location. It has the largest rescue boat used on any Shell facility, which has room for 24 people. The living quarters are blast-resistant. Perdido's helipad can accommodate two Sikorsky S-92 helicopters that can carry 19 passengers each.