MainPower


MainPower New Zealand Limited is an electricity distribution company, based in Rangiora, New Zealand, responsible for electricity distribution to over 37,000 customers in the Canterbury region north of the Waimakariri River. MainPower was formed in 1994, after the Energy Companies Act 1992 required the North Canterbury Electric Power Board to reform into a commercial power company. More reforms in 1998 required electricity companies nationally to split their lines and retail businesses, with MainPower retaining its lines business and selling its retail business to Contact Energy.
MainPower has initiated a number of local generation projects, including the Mount Cass Wind Farm and Cleardale Hydro Power Station.

Electricity network

MainPower has a total service area of, covering the Waimakariri, Hurunui and Kaikoura districts. The area includes the towns of Kaiapoi, Rangiora, Oxford, Woodend, Pegasus, Amberley, Waipara, Culverden, Cheviot, Hanmer Springs and Kaikoura.
MainPower takes electricity from Transpower's national grid at five grid exit points : Kaiapoi, Southbrook, Ashley, Waipara and Culverden. It operates 4,873 km of circuits at 66,000 and 33,000 volts for subtransmission, and 22,000 and 11,000 volts for distribution. As is standard in New Zealand, electricity is delivered to homes at 230/400 volts.
In 2011, MainPower purchased the Kaikoura GXP and Culverden to Kaikoura 66 kV transmission line from Transpower. In 2015, MainPower completed works to up-rate the network west of Rangiora towards Oxford to 66/22 kV. Other projects in progress include upgrading the 33 kV subtransmission line between Cheviot and Kaikoura to 66 kV, and preparing for a new "Rangora East" GXP between Rangiora and Woodend to supply Woodend and Pegasus, offloading Kaiapoi GXP.
ParameterValue
Total system length4,900 km
66 kV136 km
33 kV227 km
22 kV886 km
11 kV2,680 km
Single wire earth return 119 km
Low voltage 852 km
Street lighting397 km
Customer connections42,698
System maximum demand109 MW
System electricity delivered646 GWh

In the year to 31 March 2015, the MainPower network had a SAIDI of 164 minutes, meaning the average customer experiences 2.75 hours without electricity every year.