Line 1 (Lanzhou Metro)


Line 1 of the Lanzhou Metro is a subway line in Lanzhou running from to, has 20 stations and is long. It opened on 23 June 2019.

History

Line 1 started construction on July 9, 2012. Line 1 is with 20 stations. The line is completely underground. Line 1 opened on 23 June 2019. The operating speed will be. The stations are fitted with platform screen doors. The first two metro lines in Lanzhou will cost about 23 billion yuan and be completed by 2020.
On 22 October 2015, a fire broke out at the construction site of Donggang station. No casualties were reported by authorities.
The China Association of Metros has awarded an innovation award for the techniques used for the tunnel sections of Line 1's first phase under the Yellow River. Line 1 is the first subway in China to tunnel under the Yellow River.

Opening timeline

Stations

Operation

Predictions estimate 190,000 passengers per day using Line 1.

Fares

The fare price is distance based as following:
Distance Fare
0-4
4-8
8-12
12-18
18-24
24-32
32-40

Service

Trains run between 6:30 until 22:00. The travel time between the two termini is roughly 45 minutes.
It is understood that the initial operation time of Line 1 is from 6:30 to 22:00, and the daily operation service is 15 hours and 30 minutes. The single-line operation time is about 45 minutes, giving an average travel speed of.