Kakrapar Atomic Power Station


Kakrapar Atomic Power Station is a nuclear power station in India, which lies in the proximity of the city of Vyara in the state of Gujarat.

Phase I

Phase I consists of two 220 MW pressurised water reactor with heavy water as moderator. KAPS-1 went critical on 3 September 1992 and began commercial electricity production a few months later on 6 May 1993. KAPS-2 went critical on 8 January 1995 and began commercial production on 1 September 1995. In January 2003, CANDU Owners Group declared KAPS as the best performing pressurised heavy water reactor.
KAPS-2 was shut down after a coolant channel leak in July 2015 and a similar issue forced the shutdown of KAPS-1 in March 2016. After a replacement of coolant channels and feeder tubes, KAPS-2 attained criticality in September 2018. Maintenance on KAPS-1 was completed ahead of schedule and was brought to operation on 19 May 2019.
The construction costs were originally estimated to be ₹382.52 crore; the plant was finally finished at a price of ₹1,335 crore.

Phase II

In 2007 the Indian government approved outline plans to build two indigenously-designed IPHWR-700 reactors, with two sister reactors a little later at Rajasthan Atomic Power Station. In 2009 approval was confirmed, and site preparation was completed by August 2010. First concrete for Kakrapar 3 and 4 was in November 2010 and March 2011 respectively with operation originally expected by early and late 2018 respectively.
The project over-ran largely due to tuning of the IPHWR-700 design and slow delivery of supplies. Operation is now expected by October 2020 and September 2021 respectively. Unit 3 achieved first criticality on 22 July 2020.

Units

Incidents