Jakarta Outer Ring Road 2
Jakarta Outer Ringroad 2 or JORR 2 is an under-construction toll road circling the Greater Jakarta area, running roughly parallel with the Jakarta Outer Ring Road in Indonesia. This toll road will connect Soekarno-Hatta International Airport to Cilincing, crossing West Jakarta, Tangerang, South Tangerang, Depok, Bogor Regency, Bekasi Regency, Bekasi city and North Jakarta. It is expected to be able to relieve the traffic of other toll roads in the Greater Jakarta area. As of December 2019, only 11,135 kilometers has been operated, targeted to be fully operational by end of 2020.
The length of this toll road is 110 kilometers which is divided into seven sections, being Cengkareng-Kunciran, Kunciran-Serpong, Serpong-Cinere, Cinere-Jagorawi-Cimanggis, Cimanggis-Cibitung, Cibitung-Cilincing, and access to Tanjung Priok.
Sections
JORR 2 is divided into several sections:Section | Length | Main Concession by | Remarks |
Cengkareng-Batu Ceper-Kunciran | 14.1 km | PT Jasamarga Kunciran Cengkareng | 2012: Land acquisition, 2013: Construction, 2014: To be operated Expected to be completed by August 2018. |
Kunciran–Serpong | 11.2 km | PT Marga Trans Nusantara | Opened. |
Serpong–Cinere | 10.1 km | PT Cinere Serpong Jaya | July 2014: Construction, April 27 2015: To be operated November 20, 2015: not operated yet |
Cinere-Jagorawi | 14.6 km | PT Translingkar Kita Jaya | Partially opened |
Cimanggis-Cibitung | 26 km | PT Cimanggis Cibitung Tollways | Under construction |
Cibitung-Cilincing | 34 km | PT MTD CTP Expressways | Under construction |
Access to Tanjung Priok | 16.67 km | Hutama Karya | Operational since 2017. |