Glassboro–Camden Line


The Glassboro–Camden Line is an diesel multiple unit light rail system planned for the southwestern part of New Jersey in the United States. At its northern end in Camden it will connect with the River Line with which its infrastructure and vehicles will be compatible. At the northern terminus, the Walter Rand Transportation Center, paid transfers will be possible to the PATCO Speedline. The route will generally follow the right of way of Conrail's South Jersey/Philadelphia Shared Assets Operations Vineland Secondary freight rail line which continues beyond the light rail terminus in Glassboro. The project is part of a greater plan to expand public transportation in the Delaware Valley metro area.

Background

In the early 1990s, NJT commissioned a major investment study to look examine mass transit options for the South Jersey region in Burlington, Camden, and Gloucester. A rail connection from Glassboro was proposed in the report released in 1996.
In May 2009, New Jersey Governor Jon S. Corzine and the Delaware River Port Authority announced the project. It was expected to cost $1.8 billion and be completed in 2019.

Route

Located within Camden County and Gloucester County the line would include fourteen stations in Camden, Gloucester City, Westville, Brooklawn, Woodbury, Woodbury Heights, Wenonah, Mantua, Sewell, Pitman, and Glassboro.
In a non-binding referendum, Wenonah citizens voted against allowing a station in town. The town council also passed such a resolution.

Vineland Secondary right-of-way and freight rail

The West Jersey Railroad was granted its charter by the state on February 5, 1853, to build a line from Camden to Cape May. The line was built with the backing of the Camden and Amboy Railroad from Camden to Glassboro, with the first 8.2 miles of the line using the abandoned ROW built by the Camden and Woodbury Railroad to Woodbury.
In 1896 the Pennsylvania Railroad consolidated all its railroads and several smaller properties in southern New Jersey into the West Jersey and Seashore Railroad. In 1932, the PRR and Reading Company merged their southern New Jersey railroad lines into one company, the Pennsylvania-Reading Seashore Lines. The line was electrified between 1906–1949. In 1968 New York Central Railroad was merged into the PRR becoming Penn Central, which was bankrupt by 1970. The last passenger train ran in 1971.
The line came under the auspices of Conrail. Following the purchase and division of Conrail it was designated part of the South Jersey/Philadelphia Shared Assets Area. Known as the Vineland Secondary it is owned, operated and maintained by Conrail, the terminal railroad, for the exclusive benefit of CSX Transportation and Norfolk Southern Railway. The Vineland Secondary begins at Pavonia Yard in Camden and heads south. It has a spur serving the Port of Camden. It continues another to Millville.

Regional rail and bus rapid transit

The Glassboro–Camden Line is part of a broader plan to expand a regional multimodal transportation network in Delaware Valley metro area including service across the Delaware River to Philadelphia. Other elements of network would include additions and adjustments to PATCO Hi-Speed Line and Atlantic City Line and the development of new system of bus rapid transit in New Jersey. The region is served by NJT buses 400–499.
The bus rapid transit component would be developed along the heavily traveled corridor comprising I-676, Route 42, and Route 55
The southern end of the system would be a newly constructed park and ride in Deptford on Route 55 and an expanded one in Winslow with peak hour buses running at 10–15 minute intervals. Travelling northwest the two lines would converge to pass through downtown Camden, where transfers would be possible for other components of the network, including at the Walter Rand Transportation Center. They would then continue over the Benjamin Franklin Bridge, equipped with reversible or contra-flow lanes to a point near Philadelphia City Hall. Depending on approval and funding, the BRT system could be completed by 2020.

Funding

In July 2012, NJT received $2.6 million in federal funding to advance the project.
In July 2014 the Federal Transit Administration said it would not proceed with a required environmental study because no owner or operator has been identified. While the Delaware River Port Authority is overseeing the $8.1 million environmental study, the agency has not agreed to build or run it. New Jersey Transit has agreed to fund the $8.1 million study, but has also not committed to building or running it. As of 2016, there was no funding for the project.
As New Jersey raised its gas taxes in 2016, the line was targeted to receive funding for construction. an environmental impact report is expected by the end of the year. As of May 2020, the study has not been completed and the study team has shut down its website which had not been updated for several years. Any possible advancement of the project is unlikely to take place until after 2025 according to the vice chairman of the Delaware River Port Authority. It is expected that engineering work, if ever approved, would take a minimum of 18 months.