Forward Thrust
The Forward Thrust ballot initiatives were a series of bond propositions put to the voters of King County, Washington in 1968 and 1970, designed by a group called the Forward Thrust Committee. Seven of the twelve propositions in 1968 were successful; four of the remaining propositions were repackaged for a vote in 1970, when they were defeated in the darkening local economic climate of the Boeing Bust.
The initiatives were variously under the aegis of METRO, King County, and the city of Seattle. The Forward Thrust Committee was founded by James R. Ellis and effectively disbanded shortly after the 1970 defeats. It disbanded formally in 1974. Seattle Mayor Dorm Braman was also a strong backer of the 1968 initiatives.
The US$118 million passed in 1968 in support of the Department of Parks and Recreation was, at the time, the largest parks and recreation bond issue ever passed in the United States.
The failure of the rapid transit propositions meant that a nearly $900 million federal funding earmark that had been secured by U.S. Senator Warren Magnuson if local bonds passed went instead to fund Atlanta, Georgia's MARTA.
Results
The elections took place February 13, 1968 and May 19, 1970. Each initiative required a 60% supermajority to pass. The results were as follows; bold typeface indicates successful propositions:Year | Initiative | US$ amount | Yes | % Yes | No | % No | Result |
1968 | METRO Proposition 1: Rapid Transit | $385M local + $765M federal | 97,339 | 50.8% | 94,187 | 49.2% | Failed |
1968 | METRO Proposition 2: Transit System Administration | N/A | Metro Council 75,808 | 46.8% | New Commission 86,202 | 53.2% | Voided by failure of Metro Prop. 1 |
1968 | County Proposition 1: Youth Service Center | $6.1M | 174,749 | 72.4% | 66,594 | 27.6% | Passed |
1968 | County Proposition 2: Multipurpose Stadium | $40M | 151,489 | 62.3% | 91,499 | 37.7% | Passed, resulted in the Kingdome |
1968 | County Proposition 3: Community Centers | $26.2M | 136,804 | 58.7% | 96,129 | 41.3% | Failed |
1968 | County Proposition 4: Arterial Highways | $81.6M | 147,379 | 62.2% | 89,489 | 37.8% | Passed |
1968 | County Proposition 5: Storm Water Drainage | $68M | 139,254 | 59.3% | 95,373 | 40.7% | Failed |
1968 | County Proposition 6: Parks & Recreation | $118M | 157,323 | 64.7% | 85,790 | 35.3% | Passed |
1968 | Seattle Proposition 1: Neighborhood Improvements | $12M | 74,915 | 60.8% | 48,259 | 39.2% | Passed |
1968 | Seattle Proposition 2: Sewer Bonds | $70M | 74,852 | 62.6% | 44,596 | 37.4% | Passed |
1968 | Seattle Proposition 3: Low Income Housing | $3M | 69,089 | 57.9% | 50,057 | 42.1% | Failed |
1968 | Seattle Proposition 4: Fire Protection | $6.2M | 82,867 | 69.8% | 35,758 | 30.2% | Passed |
1968 | Seattle Proposition 5: Maintenance Shops | $3M | 66,061 | 57.6% | 48,555 | 42.4% | Failed |
1970 | $440M local $881M federal | 46% | 54% | Failed | |||
1970 | $80M | Failed | |||||
1970 | Failed | ||||||
1970 | $40.2M | Failed |