The Erie Water Works was incorporated in 1865 as the Erie Water and Gas Company to provide drinking water and fire hydrant water for the city of Erie, Pennsylvania. The Water Works, also known as the Erie City Water Authority, replaced the Erie Water Systems. Its board of commissioners operates independently of the city government.

Origins

A simple pump log system provided the first systematic water works for Erie beginning in 1840, tapping spring water on the Reed farm south of 18th Street and Parade Street. The city began inquiries towards a more substantial system beginning in 1853. A state law passed by the Commonwealth of Pennsylvania on 11 March 1857 on the formation and organization of gas and water companies was the basis for incorporation in 1865 and subsequent construction and provision of utility service.

Infrastructure

Erie's city government decided on 16 July 1866 to seek a hydraulic engineer to oversee construction. The city engaged Henry P M Birkinbine, Esq, of Philadelphia, Pennsylvania, who reported his findings on 23 February 1867. A formal contract to provide fire safety water for twenty years—50 fire hydrants at $9,000 per year—was signed by the city government but never enforced.
The location of the water works at the foot of Chestnut Street was determined in November 1867.
The West Engine Company of Norristown, Pennsylvania was contracted in November 1867 to provide two Cornish Bull engines. A single engine pumped per day, while per day were pumped when the engines were doubled. The city contracted with the Holly Manufacturing Company of Lockport, New York in 1885 to provide a Gaskill Engine to provide per day of water. That engine was installed in a new pump house on 11 June 1887.
The Erie City Iron Works was contracted in December 1867 to erect a standpipe, which eventually reached a height of, thought to have been the tallest standpipe in the world. John M Kuhn, Esq was hired in 1868 to build the standpipe tower, and Captain James Dunlap was contracted that year to construct the crib work. The foundation for the water works was excavated beginning on 7 April 1868.
The city government decided in 1870 that it needed a reservoir. Seven acres of land at the Cochran estate, south of 26th Street between Chestnut Street and Cherry Street, was acquired for that purpose in 1871. Work on the reservoir was completed in 1874.
The Chestnut Street Water Treatment Plant and Sommerheim Water Treatment Plant filter water received from Lake Erie and the Sommerheim Reservoir, which is spring fed. Sommerheim pumps of water per day to homes and businesses in Erie and surrounding communities.
Erie Water Works is the second largest consumer of electricity in Erie after GE Transportation. As a result of a vulnerability assessment conducted by the Department of Homeland Security, the Sommerheim plant is to receive a new power generation facility to back up its Penelec electrical service. The facility, which will cost $1.2 million, is to consist of two diesel-powered electric generators with a day tank and a bulk storage fuel tank.

Organization

As of 4 April 1867, three water commissioners were appointed by the judge of the Court of Common Pleas to serve staggered three-year terms: Henry Rawle, William Ward Reed , and William Lawrence Scott.
The Water Works, also known as the Erie City Water Authority, took over the Erie Water Systems as of 1 January 1992. The Erie Times-News suggests that the Water Authority replaced the Water System in 1989.

Politics