Donetsk Metro


The Donetsk Metro is a rapid transit system construction project in Donetsk. If finished, it could become the fourth metro in Ukraine. Unspecified plans for building instead an all-new light rail surface transit system are announced.

History

When the city of Donetsk reached the million inhabitants mark in the 1980s, it was entitled to build its own metro system, which was designed to follow the usual layout in the Soviet Union. In 1984 the first plans for a metro system in Donetsk were shown to the public, but construction did not immediately begin. Only after Ukraine gained independence, the Cabinet of Ministers issued a decree on 30 December 1991 to build the new underground metro system in Donetsk. The first investigation work began in 1992, and construction commenced the same year, with completion scheduled for 2002.
In 1995, due to the poor financial situation of the Donetsk municipality, the completion date was postponed to 2005. On September 5, 1997, the Prime Minister of Ukraine, Valeriy Pustovoitenko, ordered that the first line of the system should be open to the public in 8 years. In 2000, the first work on four of the six underground stations began. However, the financial situation of Donetsk did not improve. In June 2003, the financial problems affected the metro workers - after seven months of work, no more wages could be paid. By then nearly 300 million Hryven had been spent on the project.
In 2004 the Ukrainian government assured further means for the completion of the metro by 2010. By 2007 this seemed over-optimistic due to the slow pace of construction work. However, it later emerged that Donetsk would be one of the host cities for the Euro 2012 football championships, raising hopes for the Metro to be opened by then, although the budget that had been allocated was clearly insufficient at the time.
In 2009 funding of the project was disrupted so severely that construction workers staged several strikes to demand payment of their salaries. The city mayor Oleksandr Lukianchenko informed on May 22 that the planned 500 million hryvnia for the metro the city of Donetsk has never received.
In 2011 the city mayor announced that construction was to be suspended indefinitely due to continuing underfunding and inability to finish a first line in time for Euro 2012.
In 2012 the Vice-Prime-Minister Borys Kolesnikov stated that Ukrzaliznytsia was to start to work on the project of ground-level metro in Donetsk. The goal was to open the first line of metro no later than December 2014.
Due to the Russian military intervention in Ukraine in 2014, the work on the metro line has completely stopped. In December 2014 the Russian-installed Donetsk People's Republic set up a commission to discuss the future of the Donetsk metro. The war has greatly compromised most of economic projects that were planned in the Donetsk area due to the chronic socio-economical instability it triggered.

The original project

The first underground line of the system, which will carry the name Proletarsko-Kyivs'ka Line, is to be long and have six stations: Proletars'ka, Chumakovs'ka, Chervone Mistechko, Mushketovs'ka, Livoberezhna, and Politechnichnyi Institut.
The system's red line, Proletarsko-Kyivska, is planned to extend with 15 stations. Additionally, the blue line, Shakhtarsko-Makiyivs'ka Line, is planned to extend. Finally, the green line, Petrovs'ko-Chervonohvardiyska Line, is to have 14 stations. In its final stage, the Donetsk Metro is planned to be long, with a total of 46 stations.