DART Underground
DART Underground, previously known as the Interconnector, is a proposed mainline-rail tunnel in Dublin, Ireland. First proposed in 1972, as of 2019 it was not funded or scheduled. The National Development Plan for the period 2018-2027 proposes that a route for the proposed tunnel and line be established within that period, but does not include any funding for works or other developments.
The original plans, which propose an expansion of the electrified Dublin Area Rapid Transit network, projected the development of a tunnel between Heuston Station and Pearse Station. It had been planned to leave an existing line, via the Phoenix Park Tunnel, idle in the event of the scheme being built. This line however was subsequently reopened, connecting Heuston station with Dublin's Docklands - a cross-city connection which the DART Underground scheme was supposed to achieve. Accordingly, when the Irish Government published a new national spatial strategy in 2018, the revised plans dropped the DART Underground scheme in favour of these existing lines. Having previously secured planning consent, the project was initially deferred until after 2016, and by 2015, it had been announced that the project would be redrafted to a lower cost design. In October 2016, a "scaled down" plan was published with a potential commencement date "in 2020". As of September 2017 however, it was suggested that the developments would be deferred until after 2030, with the National Transport Authority undertaking a review of the project and its route; this review projected to complete sometime between 2018 and 2027.
History
DART Underground was first proposed in 1972 in the "Transportation in Dublin" study conducted by An Foras Forbartha, an anteceding body to Forfás as an underground rail link to connect Dublin's three main railway stations.In 1975 CIÉ commissioned the Dublin Rapid Rail Transportation Study and which recommended a 4 Phase plan including a prototypical Dart Underground:
- Phase 1 - Upgrade and electrify Howth – Bray.
- Phase 2 - An underground line from Connolly to Heuston. Rapid Transit tracks Heuston to Clondalkin overground. Spur to Tallaght from Clondalkin.
- Phase 3 - A short northerly spur off the Maynooth line to Blanchardstown and a short southerly spur to Broadstone..
- Phase 4 - A tunnel from Broadstone to Sandymount..
The plan was next proposed in 2001 as an 'Interconnector' in the Platform For Change strategy report issued by the now defunct Dublin Transportation Office or DTO.
A Railway Order permitting the construction of the project was granted in December 2011 by An Bord Pleanála. In August 2014, Minister for Transport Paschal Donohoe TD was told that both the Dart Underground and Metro North projects would have had to rely on private funding if they were to be built. In 2010, the estimated projected cost for DART Underground was €4 billion, more than half of which was expected to be provided by a public private partnership arrangement. Mr Donohoe was told he had to decide on whether to proceed with DART Underground by 24 September 2015 when the Railway Order giving authority and planning approval expires. A High Court ruling reduced the period for which compulsory purchase order notices could be issued from seven years to 18 months. The NTA's Greater Dublin Area draft Transport Strategy 2016 – 2035 published in October 2015, expressed the desire to see the tunnel completed as part of the over all DART extension programme.
Delays and status
In May 2010, Iarnród Éireann anticipated that if construction had begun in 2012 the tunnel would have been operational by 2018.On 30 June 2010, Iarnród Éireann submitted an application to An Bord Pleanála for a Railway Order for the scheme under the Transport Act 2001. Under this Act, the Board charged with considering planning, environmental and property issues regarding proposed developments.
In November 2011, the government deferred funding the project due to the decrease in capital spending until 2016 at the earliest.
A month later, in December 2011, in the Railway Order was granted for the development. The granting of the Railway Order permitted both the construction of the scheme and any necessary compulsory acquisition of property. It did not however commit funding to the project.
In September 2015, it was announced that the project had been cancelled in favour of a simpler alternative. However, it was planned to return as part of a future DART Expansion Programme, starting no earlier than at least 2020 or 2021.
As of 2016, the National Transport Authority was reviewing the DART Underground project, with a view to examining the design of the tunnels, and undertaking feasibility studies to see if it would be possible to use single-bore tunneling as opposed to twin-bore tunneling.
In September 2017, it was suggested that this review would complete early in 2018, and that -depending on the outcome of the review- works on the project would not commence until at least 2020. Revised projections suggested that it would be at least "2030 before passengers could use the new line".
By April 2018, the Irish Independent reported that the DART underground plans had been "dropped completely in favour of four new stations at ground level".
In June 2018, the then Minister for Transport stated that the review of the project's plans and route would complete during the period of the 2018-2027 National Development Plan.
Opposition
During 2010 there was opposition to the project in Dublin's East Wall area, where the tunnel would have begun and where tunnelling operations were planned to be located. Complaints were exacerbated by the suggestion that, while they would have had to endure the disturbance created by the tunneling works, East Wall residents would not gain anything from the project as they would not have easy access to a DART station - since they were roughly halfway between the Clontarf Road and Docklands stations. Complaints were also raised by residents at a Western entrance to the tunnel, at Inchicore.In late 2017, developers expressed concern that planned developments near Pearse Street Station were declined permission on the basis of their potential impact on the proposed DART Underground project.
Possible routes and stations
If routed as originally proposed, the existing DART line would be replaced by two DART lines forming a rough "X" shape - with an intersection at Pearse Station.The first of these lines would begin to the north-east of the city in Howth/Malahide, follow the existing DART line to Clontarf Road station, diverge eastward into a tunnel and to a proposed underground station in the Docklands, before heading westward under Pearse Station, St Stephen's Green and Heuston Station. It would emerge from this proposed tunnel at a new overground station on the Inchicore railway works grounds, and then follow the existing South Western Commuter line to Hazelhatch to the west of the city.
A second line would follow the existing southern DART line from Bray/Greystones to Connolly Station, from which it would diverge on the existing but un-electrified line from Connolly to Maynooth station in Kildare, with a branch off the line at Clonsilla to M3 Parkway station in Meath.
If following this plan, underground platforms would be added to the existing over-ground platforms at Spencer Dock station, Pearse station, and Stephen's Green station. New stations would also be built close to Christ Church and Inchicore.
, no route was confirmed and no station developments were planned or funded. Additional assessment was proposed to be undertaken between 2018 and 2027.