Cost database


A cost database is a computerized database of cost estimating information, which is normally used with construction estimating software to support the formation of cost estimates. A cost database may also simply be an electronic reference of cost data.

Overview

A cost database includes the electronic equivalent of a cost book, or cost reference book, a tool used by estimators for many years. Cost books may be internal records at a particular company or agency, or they may be commercially published books on the open market. Well known publishers include RSMeans, Craftsman Book Company, Gulf Publishing Company, Cost Data Online, Frank R. Walker Company, BNI Building News, and Design & Construction Resources.
The cost database may be stored in relational database management system, which may be in either an open or proprietary format, serving the data to the cost estimating software. The cost database may be hosted in the cloud. Estimators use a cost database to store data in structured way which is easy to manage and retrieve.

Details

Costing data

The most basic element of a cost estimate and therefore the cost database is the estimate line item or work item. An example is "Concrete, 4000 psi," which is the description of the item. In the cost database, an item is a row or record in a table and the description is a column or field for that record. Concrete may also be considered to be a material resource. In some systems, estimate line items and resources are the same, in other systems, various resources may be included with a line item. Other examples of resources are labor resources, such as carpenters, and equipment resources, such as cranes. Labor and equipment resources can be combined into a crew, which is then the assumed crew which will install the item or perform the work. Resources and crews can be stored as data in the cost database and can also be related to work items.
Examples of cost database line items:
IdentifierDescriptionUnit of MeasureCrewProduction RateMaterial Price
1Concrete, 4000 psi cyCP-013.00 cy/hr112.00
4023Water closet, wall hungeaPB2.50 hr/ea620.00
6119Motor starter, magnetic, FVNR, 10 hp size 1eaEL3.50 hr/ea262.00

Examples of cost database labor resources:
IdentifierDescriptionUnit of MeasureBase PriceBenefitsInsurancesPayroll Taxes
CACarpenterhour37.3212.955.014.56
CMCement Masonhour32.518.232.113.90
LALaborerhour26.465.165.723.89

Examples of cost database equipment resources:
IdentifierDescriptionUnit of MeasureBase PriceFuelFilters, Oil, Grease
cv1Concrete vibratorhour0.720.210.02
ex2Excavator, track-mounted, 1-1/2 cy hour42.0048.256.12
cr100Crane, track-mounted, lattice boom, 100 ton hour82.5059.168.27

Examples of cost database crews:
IdentifierDescriptionUnit of MeasureResource 1Quantity 1Resource 2Quantity 2Resource 3Quantity 3
CP-01Concrete placementhourCA1LA3cv11
EX-01General excavationhourOP1LA2ex21

Factor and adjustment data

Various factors and adjustments may be useful in the estimating process. Some examples include:
Data which may be used to organize a cost estimate into groups and levels, and to summarize the cost details can also be part of a cost database. A popular coding system which can be applied to construction cost estimates is MasterFormat. Another coding method is Uniformat. Also, various types of work breakdown structures or WBS may be used. It may also be useful to assign the costs to a chart of accounts or COA. Other organizational needs include:
All of these represent organizational data which can be stored in the cost database and used to support the cost estimate.

Calculational data

Data which can be used to calculate quantities and costs can also be part of a cost database. For example, there are various formulas for calculating the area of shapes, the volume of solids or spaces, and the weight of materials. There are defined unit properties of materials also. Materials each have certain densities or unit weights. Reinforcing bars are produced in certain sizes, with certain unit weights. Additionally, data which helps calculate the selection or specification of estimate contents can be included.