California High-Speed Rail


California High-Speed Rail is a publicly funded high-speed rail system under construction in the U.S. state of California. It is projected to connect the Anaheim Regional Transportation Intermodal Center in Anaheim and Union Station in Downtown Los Angeles with the Salesforce Transit Center in San Francisco via the Central Valley, providing a one-seat ride between Union Station and San Francisco in 2 hours and 40 minutes, a distance of. Future extensions are planned to connect to stations in San Diego County via the Inland Empire, as well as to Sacramento.
CAHSR plans to operate on dedicated, grade-separated tracks for the entirety of its route between San Jose and Burbank with speeds of up to, with early ridership projections for the San Francisco to Los Angeles leg at 28.4 million per year. The San Francisco–San Jose and Los Angeles–Anaheim sections will be shared with local trains in a "blended system". The project is owned and managed by the state of California through the California High-Speed Rail Authority. The Bakersfield to Los Angeles segment would be the first instance of a direct passenger train route between the cities since the termination of the Southern Pacific Railroad's San Joaquin Daylight in 1971.
The CAHSRA was established by an act of the California State Legislature and tasked with presenting a high-speed rail plan to the voters. This plan, Proposition 1A, was presented to and approved by voters in 2008 and included a $9-billion bond to begin construction on the initial leg of the network. Construction began in 2015 after a groundbreaking ceremony in Fresno. The ARRA funding agreement, which CAHSR intends to use to build the Central Valley segment, specifies a completion date of December 31, 2022, and the 2018 draft Business Plan calls for opening the initial operating segment between San Jose Diridon station and Bakersfield in 2027. The complete first phase between San Francisco and Anaheim is expected in 2033. Phase 2 extensions to Sacramento and San Diego are still in the planning stages.
On February 12, 2019, Governor Gavin Newsom in his first State of the State address announced that, while work would continue on the Central Valley segment from Bakersfield to Merced, the rest of the system would be indefinitely postponed, citing cost overruns and delays.
Project costs have escalated significantly from an initial estimate of $33.6 billion in 2008 for the Anaheim to San Francisco section according to the 2008 business plan, and a $40 billion total figure given to voters whose approval was sought in 2008. The 2008 business plan proposed a 2028 completion date for Phase 1 and a one-way fare of $55 from Los Angeles to San Francisco. In 2012 the Authority re-estimated the project's cost at $53.4 billion or $68.4 billion. Federal funds are dependent upon rail service, though not necessarily high-speed, starting on operational rails by December 2022. In 2018 the Authority pushed estimated costs to between $63.2 billion and $98.1 billion and delayed initial service to 2029, with Los Angeles to San Francisco service in 2033. Environment reviews for the entire San Francisco to Anaheim route would continue. The cost for Bakersfield to Merced is $12.4 billion.

Route and stations

On August 13, 2008, California Assembly Bill 3034 was approved by the state legislature and signed by Governor Arnold Schwarzenegger on August 26, 2008. The bill was submitted to California voters in the November 2008 election as Proposition 1A and approved. With the voter's mandate, AB 3034 specified certain route and travel time requirements. Among these were that the route must link downtown San Francisco with Los Angeles and Anaheim and must link the state's major population centers together, "including Sacramento, the San Francisco Bay Area, the Central Valley, Los Angeles Basin, the Inland Empire, Orange County, and San Diego." The first phase of the project must link San Francisco with Los Angeles and Anaheim. Up to 24 stations were authorized for the completed system.
This system was scheduled be built in two phases. Phase 1 was to be approximately long, with completion expected in 2029. Phase 1 would connect the downtowns of San Francisco, Los Angeles, and Anaheim using high-speed rail through the Central Valley. In Phase 2, the route was planned to be extended north from the Central Valley to Sacramento and east from Los Angeles through the Inland Empire and then south to San Diego. Upon completion the total system length would have been approximately.
On February 18, 2016, the Rail Authority released its 2016 Draft Business Plan, which significantly altered its near-term plans for the system implementation. While construction was always intended to begin in the Central Valley, the Initial Operating Section has always had two options: extend from the Central Valley northward toward the Bay Area, or southward to Southern California. In the 2012 and 2014 Business Plans the goal was to implement the IOS-South, but a 2016 analysis of the funding available and time necessary to bring an IOS online the rail authority proposes the IOS-North be implemented instead. The proposal, named the Silicon Valley to Central Valley Line, is expected that sufficient funding will be available to bring this segment online by 2025. The rail authority state its commitment to pursue additional funding to complete the Phase 1 system by 2029.
The updated business plan also reduced the cost of the system from US$67.6 billion to US$64.2 billion for Phase 1; this included a savings of US$5.5 billion based on actual experience, improved plans, and other feedback, but also an additional US$2.1 billion cost for improvements to the Los Angeles to Anaheim corridor. The 2016 Business Plan estimated the cost to completion of the Silicon Valley to Central Valley line was US$20.6 billion. The public had 60 days, from February 19, 2016, to submit comments on the Draft 2016 Business Plan to the rail authority. The plan was adopted by the rail authority in April 2016, and submitted by legal requirement to the California State Legislature on May 1, 2016.
The Initial Construction Segment of high-speed tracks runs from Merced to Bakersfield in the Central Valley. Simultaneously with the ICS construction, there are "bookend" and connectivity investments including electrification of the San Francisco Peninsula Corridor used by Caltrain, improvements to tracks and signaling for both Metrolink in the LA area and Caltrain, and better passenger interconnections for Caltrain, Amtrak, and other Northern California rail lines.

Phase 1

All stations in this table represent proposed service. Station names in italics are optional stations that may not be constructed. In most cases existing stations will be re-purposed for high-speed rail service, with the exception of completely new stations at Merced, Fresno, Kings–Tulare, and Bakersfield.
Note: The California High-Speed Rail Authority considered a mid-peninsula station in Redwood City, Mountain View, or Palo Alto, but it was removed from the business plan in May 2016 due to low ridership projections, although the possibility was raised of adding one in the future.

Phase 2

In 2015, the following stations and options were proposed. Existing train stations, if any, are linked. There is often a choice of alignments, some of which may involve the construction of a new station at a different location.
;Sacramento extension
The segment from Merced to Sacramento will be built on dedicated high-speed rail tracks and go to:
;San Diego extension
The southernmost segment from Los Angeles to San Diego will be built on dedicated high-speed rail tracks with several routing and stations options. Key stations are identified as:
Trains may additionally call at:
Proposals for services through a future second Transbay Tube, a San Jose–Oakland line, and a Stockton–Union City line have been studied but are not in the Phase 2 plan adopted by voters statewide.

History

Legislative

In 1996 the California High-Speed Rail Authority was established to begin formal planning in preparation for a ballot measure in 1998 or 2000. The CHSRA, a state agency run by a board of governors, is required by law to operate without a subsidy, and to connect the state's major cities in the Bay Area, Central Valley, and Los Angeles Basin. Phase 2 would extend the system northward through the Central Valley to the Sacramento Valley Station in Sacramento and southward through the Inland Empire to the San Diego International Airport in San Diego.
In 2008, California voters approved the issuance of $9 billion in bonds for high speed rail in Proposition 1A, a measure to construct the initial segment of the network.
On January 28, 2010, the White House announced that California would receive $2.25 billion for California High Speed Rail. Over the course of 2010 and 2011, the federal government awarded the Authority a further $4 billion in high-speed rail funding.
In June 2014 state legislators and Governor Jerry Brown agreed to apportion the state's annual cap-and-trade funds so that 25% goes to high speed rail. The state's Legislative Analyst's Office estimated that cap-and-trade income in 2015 and 2016 could total $3.7 billion, of which $925 million would be allocated to HSR. The LAO's predictions were proven incorrect in its own revised report dated May 26, 2016, "State auction revenue will be about $1.8 billion in 2015-16" due to a weak May 2016 auction.
On September 30, 2015, the Authority posted the names of 30 large firms who were interested in financing, constructing, and operating the California HSR system.
Proposition 1A and other legislation set certain performance standards for the project:
In February 2019, parts of the project not already under construction were postponed for a number of reasons.

Legal

In 2014, the CHSRA was challenged on its compliance with its statutory obligations under Proposition 1A
. The case was split into two parts. The ruling in the first was that the requirements for the financing plan, environmental clearances, and construction plans did not need to be secured for the entire project before construction began, but only for each construction segment. The second part considered three Proposition 1A legal requirements: Can the train travel from Los Angeles to San Francisco in two hours and 40 minutes? Will the train require an operational subsidy? Does the new "blended system" approach meet the definition of high-speed rail in Proposition 1A? Judge Kenny ruled on March 8, 2016, that although serious issues were raised, they are not "ripe for review" and that he noted "the authority may be able to accomplish these objectives at some point in the future." This did not preclude the possibility of future legal action against the Authority on these issues.
On December 15, 2014, the federal Surface Transportation Board determined that its approval of the HSR project in August "categorically preexempts" lawsuits filed under the California Environmental Quality Act. This determination is still being tested in the California courts in a similar case, Friends of Eel River v. North Coast Railroad Authority.

Construction

On December 2, 2010, the Authority Board of Directors voted to begin construction on the first section of the system from Madera to Fresno. Fresno hosted a groundbreaking ceremony on January 6, 2015, to mark the commencement of sustained construction activities.
In July 2012, the California legislature and Gov. Jerry Brown approved construction of the high-speed system.

Speed requirements

According to Proposition 1A, the train must be electric and capable of a sustained operating speed of no less than. There are also a number of travel time benchmarks. The important benchmarks applicable to Phase 1 of the project are: a maximum nonstop travel time between San Francisco and San Jose of 30 minutes, and a maximum nonstop travel time between San Jose and Los Angeles of 2 hours and 10 minutes. In addition, the time between successive trains must be less than 5 minutes.
Maximum nonstop travel times for each corridor must not exceed the following times, according to Proposition 1A:
  1. San Francisco–Los Angeles Union Station: 2 hours, 40 minutes
  2. Oakland–Los Angeles Union Station: 2 hours, 40 minutes
  3. San Francisco–San Jose: 30 minutes
  4. San Jose–Los Angeles: 2 hours, 10 minutes
  5. San Diego–Los Angeles: 1 hour, 20 minutes
  6. Inland Empire–Los Angeles: 30 minutes
  7. Sacramento–Los Angeles: 2 hours, 20 minutes
There have been some comments by critics that the proposed system will not meet the Proposition 1A requirement of downtown San Francisco to Los Angeles travel time of 2 hours and 40 minutes.
The Authority's plan is close to the requirement, but does push the limits of conventional HSR speed.
Both the Due Diligence Report and Updated Due Diligence Report state that no existing high-speed system currently meets the proposed operation speed and safety goals. It notes that the highest cruising HSR speed in the world on production runs is about in France, and this is significantly less than the sustained speed of the CHSRA plan requires. They also note safety concerns in running at top speed through highly populated urban areas such as Fresno. For three years Chinese HSR trains ran at, but the speeds were reduced due to safety concerns and – mostly – costs. In fact a Siemens Velaro trainset without any modifications has posted a speed record well in excess of, though economic considerations keep them limited to in revenue service. The French Alstom TGV Duplex is also able to sustain speeds of 360 km/h, as have shown several days of testing in 2008, not to mention all new TGV speed lines designed for 320 km/h are tested at the speed of 352 km/h by TGVs.
The current trainset specification requires the capability of sustained speeds of. So, ultimately it is up to the trainset manufacturers to meet the Authority's speed requirement, since the proposed route and speed do meet the Proposition 1A requirements.

Rolling stock

Acquisition

In January 2015, the California High Speed Rail Authority issued a request for proposal for complete trainsets. The proposals received will be reviewed so that acceptable bidders can be selected, and then requests for bids will be sent out. The winning bidder was projected to be selected in 2016, but plans have not yet been finalized.
It is estimated that for the entire Phase 1 system up to 95 trainsets might be required. Initially only 16 trainsets are anticipated to be purchased. Trainset expenses, according to the 2014 Business Plan, are planned at $889 million for the IOS in 2022, $984 million for the Bay to Basin in 2027, and $1.4 billion for the completed Phase 1 in 2029, for a total of $3.276 billion.
In February 2015, ten companies formally expressed interest in producing trainsets for the system: Alstom, AnsaldoBreda, Bombardier Transportation, CSR, Hyundai Rotem, Kawasaki Rail Car, Siemens, Sun Group U.S.A. partnered with CNR Tangshan, and Talgo. CSR merged with CNR in June 2015, bringing the number of companies down to eight.

Specifications

In addition to many other requirements:
One specification that is causing some difficulty is the HSR train requirement for a floor height of above the rails. This is the international standard for high-speed rail trains, but Caltrain trains have a floor height of only. In October 2014, Caltrain and the Authority agreed to work together to try to implement "level-boarding" on the shared station platforms. The Authority resisted lowering their trainset floor height, but a solution was found with Caltrain's new Stadler KISS EMUs which will feature doors at two heights, with the higher doors compatible with the CHSR platforms.
Some have expressed concerns about noise. Actually, the 96 dB limit at 350 km/h is the level reached by the 1988 TGV Atlantique, since then, aerodynamic improvements have been done on newer trains.
An additional factor for the selection of a model is the Buy America regulation. The Federal Railroad Administration has granted a waiver for just two prototypes to be manufactured off-shore before the remaining trainsets would need to be built according to the rules. These were mentioned as a significant reason that Chinese manufacturers dropped out of the XpressWest project with similar technical trainset specifications.

Operations

In April 2017, the CHSRA announced it had received five responses to its request for qualifications for the contract to assist with the development and management of the initial phase of the high speed line and be the initial operator.
In October 2017 the DB International US consortium was announced as the winner.

Economic projections

In addition to the direct reduction in travel times the HSR project will produce, there are other anticipated benefits, both general to the state, to the regions the train will pass through, and to the areas immediately around the train stations.

Statewide economic growth and job creation

In 2009, the Authority projected that construction of the system will create 450,000 permanent jobs through the new commuters that will use the system, and that the Los Angeles-San Francisco route will generate a net operating revenue of $2.23 billion by 2023, consistent with the experience of other high-speed intercity operations around the world. The by Parson Brinkerhoff also indicated substantial economic benefits from high-speed rail.
Even Amtrak's high-speed Acela Express service generates an operating surplus that is used to cover operating expenses of other lines, Amtrak says. Amtrak calculates this in a way which is not equivalent to the way that it determines the costs of other train services, and most of the Acela's costs for using track and fuel are paid for by Silver Service long distance trains, according to TRAINS Magazine's Fred Frailey.
The 2012 Business Plan also estimates that the Initial Construction Segment construction will "generate 20,000 jobs over five years," with the Phase 1 system requiring 990,000 job-years over 15 years, averaging 66,000 annually.

Environmental benefits

According to a fact sheet on the Authority website the environmental benefits of the system include:
In its 67-page ruling in May 2015, the federal Surface Transportation Board noted: "The current transportation system in the San Joaquin Valley region has not kept pace with the increase in population, economic activity, and tourism.... The interstate highway system, commercial airports, and conventional passenger rail systems serving the intercity market are operating at or near capacity and would require large public investments for maintenance and expansion to meet existing demand and future growth over the next 25 years or beyond." Thus, the Board sees the HSR system as providing valuable benefits to the region's transportation needs.
The San Joaquin Valley is also one of the poorest areas of the state. For example, the unemployment rate near the end of 2014 in Fresno County was 2.2% higher than the statewide average. And, of the five poorest metro areas in the country, three are in the Central Valley. The HSR system has the potential to significantly improve this region and its economy. A large January 2015 report to the CHSRA examined this issue.
In addition to jobs and income levels in general, the presence of HSR is expected to benefit the growth in the cities around the HSR stations. It is anticipated that this will help increase population density in those cities and reduce "development sprawl" out into surrounding farmlands.

Ridership and revenue concerns

In May 2015, the Los Angeles Times published an article by critics on the estimated operational revenue of the system in "Doing the math on California's bullet train fares". The article raised a number of doubts that the system could be self-supporting, as required by Prop 1A, and ended by quoting Louis Thompson who said "We will not know until late in the game how everything will turn out."
The Due Diligence Report projected fewer riders by 2030 than officially estimated: 23.4 to 31.1 million intercity riders a year instead of the 65.5 to 96.5 million forecast by the Authority and later confirmed by an independent peer review.
The Authority's ridership estimates initially were unrealistically high, and have been revised several times using progressively better estimating models, including risk analysis and confidence levels. The 2014 study estimated the following ridership/revenue figures:
2022 : 11.3 million riders / $625 million
2027 : 19.1 million riders / $1055.6 million
2029 : 28.4 million riders / $1350.4 million
2040 : 33.1 million riders / $1559.4 million

Project budget concerns

The project's cost and scope have long been a source of controversy. The project was sold to voters with a projected cost of $40 billion in 2008. Election year proponents also promised a 2028 completion date, and a $55 one-way Los Angeles to San Francisco fare. In 2012 the Authority re-estimated the project's year-of-expenditure cost at $68.4 billion. In 2012 the estimated cost of a fare from LA to San Francisco has risen to $86. In March 2018, the Authority revised its estimate to $77.3 billion and up to $98.1 billion, pushing initial service to 2029 and services from Los Angeles to San Francisco to 2033.
The Reason Foundation's Due Diligence Report projected that the final cost for the complete system would be $65.2 to $81.4 billion. Current estimates from the Authority estimate a total cost for Phase 1 of $64.2 billion. The Authority is using Design-Build construction contracts to counter the tendency toward cost over-runs. All of the construction is to be done via "design-build" proposals wherein each builder is given leeway in the design and management of construction, but not the ability to run back with contract change orders except for extraordinary problems. The builder is given specifications but also given the freedom to meet them in their own way, plus the ability to modify the construction plans in an expeditious and cost-effective manner.
The California Legislative Analyst's Office published recommendations on May 10, 2011, which they said will help the high-speed rail project be developed successfully. They recommended that the California legislature seek flexibility on use of federal funds and then reconsider where construction of the high-speed rail line should start. They also recommended that the California legislature shift responsibility away from the Authority and fund only the administrative tasks of the Authority in the 2011–12 budget.
In January 2012, an independent peer review panel published a report recommending the Legislature not approve issuing $2.7 billion in bonds to fund the project. The panel of experts was created by state law to help safeguard the public's interest. The report said that moving ahead on the high-speed rail project without credible sources of adequate funding represents a financial risk to California.
Prior to the July 2012 vote, State Senator Joe Simitian,, expressed concerns about financing needed to complete the project, asking: "Is there additional commitment of federal funds? There is not. Is there additional commitment of private funding? There is not. Is there a dedicated funding source that we can look to in the coming years? There is not." The lobbying and advocacy group Train Riders Association of California also considers that Bill SB 1029 "provides no high-speed service for the next decade".
In July 2014 The World Bank reported that the per kilometer cost of California's high-speed rail system was $56 million, more than double the average cost of $17–21 million per km of high speed rail in China and more than the $25–39 million per km average for similar projects in Europe. High real estate prices in California and three mountain ranges to cross contribute to the difference. For example, Construction Package 2-3 in the farmland of the flat Central Valley works out to $11.4 million per km, although this figure does not include electrification or property values, so it's roughly comparable internationally. Furthermore, the proposed High Speed 2 in Great Britain is estimated to be more expensive on a per mile basis than the Californian system.
As of May 2015, both construction packages awarded have come in significantly under staff estimates. For example, Construction Package 1 came in 20% under staff estimates, and Construction Package 2-3 came in under by 17% to 28%.
In December 2016, an internal-use-only draft risk assessment produced by the Federal Railroad Administration was delivered to the California Rail Authority which warned that the ICS segment could cost as much as $9.5 billion instead of the $6.4 billion originally budgeted, if certain challenges weren't addressed, including delays in environmental planning, lags in processing invoices and failures to acquire needed property. Federal Railroad Administration spokesman Matthew Lehner said that the draft risk assessment "is a standard oversight tool used on major capital projects — not just California", and he is confident the state can meet its deadline with continued focus and hard work. Concern over the article prompted the Authority to send a letter on January 13, 2017 to the Legislature that said that the characterization of cost overruns, delays, and potential lapses of funds are not borne out by the facts, and that other key federal findings were ignored. After downplaying risks of cost overruns, in January 2018 the Authority acknowledged that cost estimates for the initial segment had increased to $10.6 billion.
In 2018, it was estimated that the first phase of CHSR will cost $77 billion in year-of-expenditure dollars, assuming a 2033 completion year and 3% inflation.

Public opinion and peer review

There are two types of criticism: the legally established "peer review" process that the legislature established for an independent check on the Authority's planning efforts, and public criticisms by groups, individuals, public agencies, and elected officials.
As of the February 2015 conference Bold Bets: California on the Move?, which is hosted by The Atlantic magazine and Siemens, Dan Richard, the chair of the Authority, warned that not all issues to get the HSR system in place had yet been resolved.

Peer Review Group

The California Legislature established the to provide independent analysis of the Authority's business plans and modeling efforts. Their documents are submitted to the Legislature as needed.
The most recent critiques are , and .
Key points in the 2016 business plan review include:
Two peer studies have been made of station siting and design in Europe.
Eric Eidlin, an employee of the Federal Transit Administration, in 2015 wrote a study funded by the German Marshall Fund of the United States comparing the structural differences of the three relative to HSR and their historical development. He also focused on the issue of station siting, design, use, and impact on the surrounding community. From this, he developed ten recommendations for CASHRA. Among these are:
Eidlin's study also notes that in California there has been debate on the disadvantages of the proposed blended service in the urban areas of San Francisco and Los Angeles, including reduced speeds, more operating restraints, and complicated track-sharing agreements. There are some inherent advantages in blended systems that have not received much attention: shorter transfer distances for passengers, and reduced impacts on the neighborhoods. Blended systems are in use in Europe.
A July 2015 study by A. Loukaitou-Sideris, D. Peters, and W. Wei of the Mineta Transportation Institute at San Jose State University compared the rail systems of Spain and Germany, and how blended high-speed rail lines have succeeded there. Emphasis was also given to station siting, design, and use. Similarly to Eidlin's study, they found that the best stations not only provided high connectivity, but they also had a broader role by providing shops and services to community members as well as travelers.

Think tank studies

, the Howard Jarvis Taxpayers Association, and the Citizens Against Government Waste published a study which they named the "Due Diligence Report" critiquing the project. In 2013 Reason Foundation published an "Updated Due Diligence Report". Key elements of the updated critique include:
This 2013 critique is based on the 2012 Business Plan. Although the 2012 Business Plan has been superseded by the 2016 Business Plan, the critique does include the Blended System approach using commuter tracks in SF and LA.
James Fallows in The Atlantic magazine summarized all the public criticisms thus, "It will cost too much, take too long, use up too much land, go to the wrong places, and in the end won't be fast or convenient enough to do that much good anyway."

Public opinion surveys

The Public Policy Institute of California March 2016 Statewide Survey indicated that 63% of Californians think the project is either very important or somewhat important, but costs are an issue. Currently over 50% favor building the system, but this increases to 66% if costs could be reduced. Note that the levels of support have generally been similar since the 2012 survey.
Support also varies by location, by race, and age. Support also notably varies by political orientation. The percentage of supporters and opponents by party is: Democrat, Independent, and Republican.
Dan Richard, chair of the Authority, says in an interview with James Fallows that he believes approval levels will increase when people can start seeing progress, and trains start running on the tracks.

Related projects

XpressWest connection to Las Vegas

is a company that since 2007 has been trying to build a high-speed rail line between Southern California and Las Vegas, Nevada, part of the "Southwest Rail Network" they hope to create. The rail line would begin in Las Vegas and cross the Mojave Desert stopping in Victorville, California and terminating in Palmdale, California. This route would total about. Lisa Marie Alley, speaking for CAHSRA, said that there have been ongoing discussions concerning allowing the trains to use CAHSRA lines to go further into the Los Angeles area, although no commitments have been made as yet. While many approvals have been obtained for the rail line from Victorville to Las Vegas, the section from Palmdale to Victorville has none as yet. In September 2018, Florida-based railway company Brightline purchased the rights and assets to the connection and plan to start construction subsequently.

Alternative infrastructure proposals

Some have offered the idea that instead of risking the large expenditures of high-speed rail, existing transportation methods should be increased to meet transportation needs. In a report commissioned by the Authority, a comparison was made to the needed infrastructure improvements if high-speed rail were not constructed. According to the report, the cost of building equivalent capacity to the $68.4 billion Phase 1 Blended plan, in airports and freeways, is estimated to be $119.0 billion for 4,295 new lane-miles of highway, plus $38.6 billion for 115 new airport gates and 4 new runways, for a total estimated cost of $158 billion.
"Hyperloop" is an alternative system that Elon Musk has championed. He has criticized the high-speed rail project as too expensive and not technologically advanced enough. On August 12, 2013 he released a high-level alpha design for a Hyperloop transit system concept which he claimed would travel over three times as fast and cost less than a tenth of the rail proposal. The following day he announced a plan to construct a demonstration of the concept. Musk's claims have been subject to significant debate and criticism, in particular that the costs are still unknown and likely understated, the technology is not proven enough for statewide implementation, the route proposed doesn't meet the needs of providing statewide transportation, and it does not meet the legal requirements of Proposition 1A and so would require a whole new legal underpinning. One flaw of the hyperloop is that it can carry far fewer passengers per trip compared to high-speed rail and, as of 2019, no sizable Hyperloop prototypes have been constructed to demonstrate that such a system is possible to construct on an intercity scale.